Power Plant Circulating and Condensate Water System
← Back to projectsPower · 2023

Power Plant Circulating and Condensate Water System

Guodian Hanchuan Power

CustomerGuodian Hanchuan Power
IndustryPower
Year2023
Scope2 units / circulating and condensate water
PROJECT BACKGROUND

Project background

The plant required low NPSH, continuous operation and reliable standby switching for its circulating and condensate systems.

OUR SOLUTION

Our solution

N condensate and TOS split case pumps were combined, with NPSH, duty point and standby logic verified for start-stop and switching conditions.

N condensate pump / TOS split case pump2 units / circulating and condensate water

Results

Continuous operation and low-NPSH requirements satisfied.

Request a similar solution →